The connection between generation and demand
Electricity travels through a network of lines, transformers and substations. Adding generation in one location does not automatically create the ability to transfer its full output to every demand centre. Network planning considers equipment ratings, network topology, voltage management and the consequences of equipment outages.
What the published figures show
NTNSP’s system performance table reports 91 substations and 12,548 MVA of total capacity for 2024, compared with 90 and 12,459 MVA in 2023. These are dated infrastructure statistics. They do not describe the spare connection capacity at an individual substation today.
MVA and MW answer different questions
MVA measures apparent power; MW measures active power. Their relationship depends on power factor and the operating condition. An MVA rating should not be presented as an equivalent MW generation figure. Published capacity totals can also cover different equipment and scopes.
Keep different published totals separate
The NTNSP grid reliability overview and its system performance tables publish capacity figures with different labels and detail. LEX preserves those sources separately. The reliability overview does not state a reporting year for its annual headline figures, so LEX labels the year as unspecified.
A better question for a new project
Instead of using a national capacity total as a connection promise, ask about the proposed connection point, the network study, reinforcement requirements and applicable connection procedures. National statistics offer context; project-specific studies address the local constraints.